I came across a question below that has an answer stating to review the change and raise it to CCB instead review the impact with team or PO. Can anyone help any the choice is CCB in agile (Agile promotes collaboration and communication so analysis with team or PO wouldn't be the right answer)?
--------------------------------------
A project team is in sprint 13 of a fourteen-sprint project. The project team placed a game-changing feature on the backlog for the next release that closely resembles a feature a competitor is launching. The product owner insists on incorporating this game-changing feature in the current release.
What should be the next step for the project manager?