A high-level manager in an organization would like to use a critical project resource for a new project.
Which action should the project manager take?
1. Contact the program manager to resolve the issue
2. Request that the high-level manager provides a replacement
3. Use the Legitimate form of power to deny the request
4. Tell the team and reassign that resource's responsibilities to other team members